Conditions and stages of production of your brewery equipment

The conditions and sequence of the manufacturing stages of the equipment for your brewery are usually as follows:

  1. Coordination of terms of production, signing of the contract of production of the equipment;
  2. Advance payment (75%);
  3. Manufacturing equipment;
  4. Demonstration of the finished equipment on the territory of the enterprise;
  5. Signing of the equipment acceptance certificate;
  6. The final calculation and preparation for shipment: packaging, registration of accompanying and customs documents.
  7. Transportation of equipment (transport company or customer’s transport).
  8. Installation and commissioning of equipment on the territory of the customer (under a separate contract).
  9. Signing the act of commissioning.